- 1 - Meter Installation in 4838 Reactor Controller 1. Unplug the power cord of the 4838 controller. Remove the (2) screws located on the top/
- 2 - HTM Installation Meter Installation in 4838 Reactor Controller (continued) Meter Installation Diagram
- 3 - HTM Installation Wiring Installation in 4838 Reactor Controller 2082E pin out (pin 5 is blank) Picture of 2082E pin out Wiring diagra
- 4 - HTM Installation Wiring Installation in 4838 Reactor Controller Warning: Take care not to apply too much torque when tightening down on
- 5 - HTM Installation Wiring Installation in 4848 Reactor Controller Pin Outs: 2082E Color: Attaches to: Pin 1 Black Terminal Block 4 Pi
- 6 - HTM Installation High Temperature Module - HTM Keys command: 1. Press “SET” to select 2. Press return key move to next operation mode
- 7 - HTM Installation High Temperature Module - HTM (continued) Press “SET” and release Operation Mode Select type/value Comment HtS 0 Heat
Revision 5/14/10 Parr Instrument Company 211 53rd Street • Moline, Illinois 61265 USA 1-309-762-7716 • 1-800-872-7720 • Fax: 1-309-762-9453 E-mail: